Visit the Town of Voluntown online building and land use application portal.
The process and steps needed for filing for a Building permit in Voluntown are as follows:
1. Determine whether your lot is an approved building lot by:
Contacting the Zoning Enforcement officer at 860-376-3867
Contacting the Inland/Wetlands Enforcement Officer at 860-376-4089
2. Make sure there are no wetlands or wetland restrictions identified on the lot.
3. Provide a copy of the permit to construct a septic system: Contact UNCAS Health
4. Obtain a driveway permit:
If lot is on a town road contact the First Selectman 860-376-5880
If lot is on a state road contact the Connecticut Department of Transportation
5. A plot plan must be submitted to the Zoning Enforcement Officer and Building Official